ENGINEERED PAD (110′ X 93′ X 24″ THICK)
AVERAGE PAD THICKNESS IS 24″ (SCRAPE 6″, INSTALL APPROXIMATELY 18″ SELECT FILL AT HIGHER GRADE AREAS, AND ADD APPROXIMATELY 30″ SELECT FILL AT LOWER GRADE AREAS)
Step 1: Clear cut w/ root rake includes removing all trees, tree stumps, roots, and underbrush. After all preliminary vegetation has been removed, the entire work area is raked by a bull dozer with attached root rake too remove all roots that are beneath the ground.
Step 2: Hydro-mulching (underbrush removal). Includes mulching up of materials up to 6″ in diameter. When complete there will be a layer of mulched material that varies in size
Step 3: Scraping of vegetation (vegetation consists of grass, weeds and small saplings) along with soil beneath to the required depth. Removal of larger trees, rocks or atypical impediments. Select Fill – Sand/Clay Mix – typically consisting of 60% sand and 40% clay.